Signal · Development

Westcourt: the project's financier lists a Q3 2026 – Q4 2028 construction window

noted Aug 31, 2026

Somewhere on our Downtown Orlando map

Golden Gate Global, raising EB-5 money for the district, lists construction running Q3 2026 through Q4 2028 — a 265-key Kimpton hotel, 269 multifamily units and a 1,145-stall seven-story garage — with the offering described as nearly 50% pre-booked at $800,000 per investment. No formal groundbreaking or construction-loan closing has been announced through Aug. 31; site and enabling work was last confirmed in early May. Sources also disagree on the district's cost (Turner Construction and WFTV say $500 million; GrowthSpotter has used $900 million) and on the residence count (269 here, 270 at approval).

sourced ↗ Golden Gate GlobalPart of a bigger storyWestcourt (Sentinel site)