Signal · Development
A $219.3 million rebuild is underway at I-4 and Sand Lake Road
noted Aug 31, 2026
FDOT’s combined design-build (financial project numbers 444315-1 and 444315-3) lists the construction cost at $219,342,910.12, with The Lane Construction Corp. building a full diverging-diamond reconstruction of the interchange, longer ramps, added capacity on Sand Lake and Turkey Lake roads, and new barrier-separated westbound express lanes. A new loop ramp opened in May 2026. FDOT’s own pages disagree on the finish — one lists late 2027, its companion early 2027.