SR 516: the eastern segment is three-quarters built, and the middle segment is under way
noted Aug 31, 2026
CFX's April 2026 construction report puts Segment 3 (county line to S.R. 429, SEMA Construction) at 74.47% complete on a $231,042,075 contract that runs to April 27, 2027. Segment 2 (Cook Road to the county line, Prince Contracting, $141,133,517) started construction April 13, 2026. A correction to earlier records: the 58.5% figure reported for Segment 3 in February was the contract's time used, not work complete — the February report shows 68.12% complete.