The New Independence Parkway Extension.
Under construction · as of Jan 28, 2026
“One new mile of parkway connects Horizon West to Wellness Way in early 2027” — Sep 1, 2026.
Project · West Orange County
Under construction · as of Jan 28, 2026
“One new mile of parkway connects Horizon West to Wellness Way in early 2027” — Sep 1, 2026.
The timeline
Where is it really?
Under construction
Now
Orange County issues the Notice to Proceed: roughly one mile of new four-lane roadway from the county line to about 400 feet east of CR 545 (Avalon Road), linking U.S. 27 in Lake County to State Road 429 in Orange — two 11-foot lanes each way around a raised grass median, with lighting, landscaping and drainage.
Development · Sep 1, 2026
One new mile of parkway connects Horizon West to Wellness Way in early 2027
Crews are extending New Independence Parkway, Orange County reported in January 2026 — approximately one mile of new four-lane roadway connecting the existing parkway east of CR 545 (Avalon Road) to Wellness Way at the Lake County border. The extension carries 10-foot multiuse paths on both sides of the roadway and drainage improvements sized for long-term growth, and is expected to be completed in early 2027 as one of two new connections between Orange and Lake counties — the other being the Flemings Road Extension a few miles south.
sourced ↗Orange County Newsroom
From our comments
“Any idea when Sawgrass Bay Blvd will connect to allow access to Avalon / Western Way?”
Real comments from @theorlandoreal’s Instagram — each opens the original reel
Send this to someone
The page stays current — whoever opens it gets where it really stands, not where it stood when you sent it.
Opens for anyone. No app, no login.
That’s where it stands.
Newest signal · Sep 1, 2026
Where this isEverything about West Orange→The roomWhat neighbours are saying in West Orange→